Top Side LPG offloading Jetty, Propane BOG System and Seawater Intake and Outfall

 

Project:  

  Top Side Jetty, Propane BOG System and Seawater Intake and 

  Outfall (Detailed Eng.)

Client:  
  IOOC
Main Contractor:  
  IRITEC/ Omran Falat Co.
Engineering Subcontractor:  
  Rahbord Energy
Project Location:  
  Persian Gulf, Qeshm Island
Capacity:  

  4500 m3/hr C3 Loading, 2250 m3/hr C4 Loading

  900 m3/hr C5 Loading, 2700 m3/hr C6+ Loading

  50,000 m3/hr Seawater

  41 tone/hr BOG System Capacity

Technical Category:  
  NGL Plants
Services Performed:  

  Detailed Engineering (All Disciplines),

  Procurement  Engineering,Site Engineering & 

  As-built Drawings

Estimated Man-hour:     40,000
Project Status:     80% Progress