Top Side LPG offloading Jetty, Propane BOG System and Seawater Intake and Outfall

| Project: |
Top Side Jetty, Propane BOG System and Seawater Intake and Outfall (Detailed Eng.) |
| Client: |
IOOC |
| Main Contractor: |
IRITEC/ Omran Falat Co. |
| Engineering Subcontractor: |
Rahbord Energy |
| Project Location: |
Persian Gulf, Qeshm Island |
| Capacity: |
4500 m3/hr C3 Loading, 2250 m3/hr C4 Loading 900 m3/hr C5 Loading, 2700 m3/hr C6+ Loading 50,000 m3/hr Seawater 41 tone/hr BOG System Capacity |
| Technical Category: |
NGL Plants |
| Services Performed: |
Detailed Engineering (All Disciplines), Procurement Engineering,Site Engineering & As-built Drawings |
| Estimated Man-hour: | 40,000 |
| Project Status: | 80% Progress |